Problem
Three plants shared one capacity pool, and the planner spent four hours every morning copying data across 12 spreadsheets. One rush order forced a full re-plan: the paint line ran at capacity while CNC sat idle, and delivery promises depended on whoever happened to be planning that day.
Approach
Two weeks on site to surface the real constraints: changeover time by machine and tooling combination, operator skills by workstation, material readiness by inbound batch. Only then did automation start. A baseline schedule is generated overnight; a rush order re-plans only the affected three-day window; every result explains why a job sits where it sits. The planner confirms by dragging, and the confirmation takes effect.
Result
Scheduling dropped from four hours to 40 minutes, rush-order response from four hours to 30 minutes. Three months in, on-time delivery rose 12 points, and the same volume is planned by two people instead of three.