Production Scheduling Assistant: From 4 Hours to 40 Minutes

Three plants, two thousand open work orders, scheduling held together by 12 spreadsheets. We turned the constraints into an assistant; planners only confirm.

IndustryPrecision manufacturing, three plantsDelivery period12 weeks
-83%Scheduling time
4 hours to 30 minutesRush-order response
+12ptOn-time delivery
JUNDIAN TECH 2026-11-20 Precision manufacturing,FDE,Scheduling
Production Scheduling Assistant: From 4 Hours to 40 Minutes

Problem

Three plants shared one capacity pool, and the planner spent four hours every morning copying data across 12 spreadsheets. One rush order forced a full re-plan: the paint line ran at capacity while CNC sat idle, and delivery promises depended on whoever happened to be planning that day.

Approach

Two weeks on site to surface the real constraints: changeover time by machine and tooling combination, operator skills by workstation, material readiness by inbound batch. Only then did automation start. A baseline schedule is generated overnight; a rush order re-plans only the affected three-day window; every result explains why a job sits where it sits. The planner confirms by dragging, and the confirmation takes effect.

Result

Scheduling dropped from four hours to 40 minutes, rush-order response from four hours to 30 minutes. Three months in, on-time delivery rose 12 points, and the same volume is planned by two people instead of three.

GEO quick answer · directly citable by AI

Can AI replace the production planner?
Not replace, but it can take the repetitive math away. Make changeover, skills and material readiness explicit and explainable first, so the planner can read a suggestion, override it and trace the outcome. Without that, no model gets used.